Building your own home is the biggest project most people ever take on. Whether it's a self-build on a plot you've waited years for, or a knockdown rebuild of a house that never quite worked, the build programme moves fast, and the interior decisions arrive far earlier than most people expect.
The trouble is that nobody hands you a timeline for the inside. The architect has a programme for the drawings and the builder has one for the build, but the questions about where the sofa goes, how the kitchen works and where the lights fall tend to land on you, usually the week before they're needed.
So here is the timeline I walk our self-build and rebuild clients through: what needs deciding at each stage, and why it can't wait for the next one.
Stage One: While the Drawings Are Still Moving
This is the most valuable moment on the whole project, and the one most people miss. While the architect's plans are still being developed, everything is still cheap to change. A door can move half a metre. A window can be widened so it frames the view from the sofa rather than the side of the TV. A wall can shift to give the utility room the extra width it needs.
At this stage we're working over the architect's drawings, asking how each room will actually be used:
- Furniture layouts for every main room. Where the sofa sits decides where the sockets, the TV and the lighting go, so it needs settling first.
- The kitchen. How you cook, where the island goes, how many people sit at it, where the tall units and appliances live.
- Bathrooms and the principal suite. Which way the bed faces, where the basins go, whether the bath sits under a window or a rooflight.
- Joinery. Boot rooms, dressing rooms, media walls and alcove storage, so the walls and openings are drawn to suit them rather than the other way round.

If you're wondering whether you need an interior designer this early when you've already got an architect, I wrote about exactly that in do you need an interior designer if you have an architect? The short version: the architect designs the building, we design how you'll live in it, and the two work best side by side.
Stage Two: Before First Fix
First fix is when the electrician and plumber run their cables and pipes through the bare walls and floors. Once the plaster goes on, moving any of it means chasing walls and making good, so this is the deadline for every decision that hides inside a wall.

Before first fix you want:
- A lighting and electrical layout. Every socket, switch, downlight, wall light and pendant, drawn over the plan. This is the single drawing I'd most want on any build, and it's the one most often left to the electrician to guess.
- Wall lights and picture lights positioned. Their wiring has to be in the wall at the right height, so the furniture plan needs to be settled.
- Bathroom positions fixed. Basins, WCs, showers, concealed valves and heated towel rails all need their pipework in exactly the right place.
- Speakers, data and the TV wall. Anything built in needs its cabling now.
Drawings like these show the design intent. Your electrician, plumber and builder check and confirm everything on site, because they are the ones who know what the structure will allow.
Stage Three: While the Plaster Dries

Once the house is weathertight and plastered, it feels as though there's a breather. There isn't, quite. This is when the long-lead items need ordering so they arrive in time for second fix:
- The kitchen. Bespoke kitchens are made to order and many weeks can pass between signing off the drawings and installation.
- Bespoke joinery. Dressing rooms, boot rooms and media walls are made to the room, and good joiners book up well ahead. It's worth reading is bespoke joinery worth it? while you're weighing it up.
- Flooring, tiles and stone. Natural stone in particular can take time to arrive, and you'll want samples in the actual rooms before you commit.
- Sanitaryware and brassware. Taps, showers and basins in the finish you want are not always on the shelf.

Stage Four: Second Fix
Second fix is when the house starts to look like a home: the kitchen goes in, the bathrooms are fitted, the light fittings are hung and the doors go on. The decisions here are the ones people enjoy, but they still have deadlines.
- Light fittings chosen and on site, so the electrician can hang them at second fix rather than coming back.
- Door ironmongery, switches and sockets in a finish that suits the house. A run of brushed brass plates or a dark bronze handle changes a room more than you'd think.
- Paint colours for every room, ideally tested on the walls in the light they'll actually get.

Stage Five: Moving In
The last stage is the one that turns a new house into your home: furniture, curtains and blinds, rugs, art, lamps and the styling that makes it feel lived in from the first night. Bespoke upholstery and made-to-measure curtains are made to order, so these are best chosen while the build is still going, not once the builder has left.
I've written more about this part in how to make a new build feel like home, because a brand-new house can feel a little blank until it's properly furnished.

What About a Knockdown Rebuild?
A knockdown rebuild follows exactly the same timeline, with one advantage: you already know the plot, the light and the way you use the house you're replacing. That's hugely useful. We start by talking through what never worked in the old house, so the new one is designed around fixing it.
Where We Come In
Self-builds, knockdown rebuilds and whole-home renovations are the projects we love most, because there's so much we can still shape. We work alongside your architect and builder from drawing stage, prepare the layouts, lighting plans and joinery drawings they need, and stay with you through to the final styling. You can see how we approach them on our self-builds and renovations page, or have a look at the private new build and the Prestbury family home in our portfolio.
Planning a build in Cheshire? The earlier we talk, the more we can help. Tell us about your project and we'll arrange a complimentary discovery call.